East Franklin's McEwen Drive Rebuild, Entrance by Entrance, Through 2030

November 19, 2026

"Many people drive into this area on a country road," Franklin Mayor Ken Moore said on April 29, 2025, at the groundbreaking for the East McEwen Drive widening. The Williamson Herald reported his remark from the ceremony on Garden Club Court, just off McEwen. Nineteen months later, that country road is in the middle of becoming something else.

The road you drive to a showing on East McEwen this month is temporary. The city of Franklin and the city of Brentwood are both planning for the road it will be around 2030, and Brentwood's plans show what that road is meant to do. If you're weighing a home in McKay's Mill, along Players Mill Road, in Meade of Avalon, or near Taramore and Breezeway at the Wilson Pike end, that later road is the one you're buying next to.

The traffic had already outgrown the road

The traffic counts explain the project. Jonathan Marston, Franklin's assistant director of capital improvements, said at the groundbreaking that East McEwen went from 1,300 vehicles a day in 2005 to 13,000 a day in April 2025. That's ten times as many cars on a winding two-lane road over twenty years. Williamson Herald reported the figures, along with his description of the stretch as "as close to a mountainous roadway that we're ever going to do in Franklin."

Getting the project funded took nearly as long as the traffic took to grow. Ward 1 Alderman Bev Burger told the Williamson Herald that McEwen started at No. 47 on the city's capital projects list. Over her years in office it climbed to 32, 27, 21, 14, seven, and finally first. At the groundbreaking she called it "the largest, most ambitious road project our city has ever seen."

Where Phase 4 stands this month

Phase 4 widens 1.3 miles of East McEwen, from just east of the roundabout at Cool Springs Boulevard and Oxford Glen Drive to Wilson Pike. When it's finished, the road will have four lanes with a median, left-turn lanes where needed, curb and gutter, a sidewalk, a multi-use path, and street lighting. The city's capital improvement project page lists Phase 4 as under construction, with completion estimated for 2028. As of the page's mid-November 2026 update, the project estimate is $56.099 million. In April 2025, when the city announced the groundbreaking, the price was $45.8 million. On November 10, 2026, the Board of Mayor and Aldermen unanimously approved another $285,743.66 for the Vulcan construction contract, according to OpenTennessee's meeting summary.

For a buyer, the dollar figures matter less than the calendar. The road stays open throughout construction. City staff engineer David Hodnett, who is overseeing the work, told the January 2025 town hall that there will be disruptions to drivers' routines. "There will be some inconvenience," he said. "That's just a natural byproduct." If you close on a home off McEwen this winter, expect to live with that inconvenience for about two years.

What the plans call for at specific entrances

The city's January 2025 public meeting document laid out a tentative staging plan. It included a main detour, the closure and reconstruction of Players Mill Road, and temporary rerouted access for several tracts along the corridor. The same document said crews could blast or use rock hammering if they hit rock, and that limited night closures could happen for utility crossings. At that meeting, residents asked how hard it would be to get in and out of Players Mill and McKay's Mill during construction. Marston said homeowners near blasting work should cooperate with the pre-blast surveyor, who wants "to know as much information as they can," as the Williamson Herald reported. The Meade of Avalon HOA asked about temporary fencing between its homes and the work zone. Staff said fencing wasn't in the project's scope but that the city was open to discussing options with the HOA.

These details matter most for the largest community on the west end of the corridor. The McKay's Mill HOA describes its community as more than 1,300 single-family homes, townhomes and condos off Liberty Pike and Oxford Glen Drive, with a clubhouse, pool, playground, walking trails and green spaces. Oxford Glen Drive meets McEwen at the roundabout, and Phase 4 begins about 800 feet east of it. So a household in McKay's Mill can go in two directions, and how much the construction affects it depends on which way it usually turns. Burger said she would give homeowners associations advance notice of road closures that affect them. If you're under contract, ask the HOA what notices it has received so far.

Phase 5 shows who the road is being built for

Phase 4 widens the road that's already there. Phase 5 builds new road east of Wilson Pike to the Franklin-Brentwood city limit, between the Breezeway and Taramore neighborhoods. It will open with two lanes, graded so it can be widened to four later. The project requires upgrades to three Columbia Gulf natural gas transmission pipelines. Franklin's Phase 5 project page says the city is acquiring land and right-of-way now, puts the estimate at $18.6 million, and gives 2030 as the completion date. In January 2025, City Administrator Eric Stuckey said Brentwood would pay 59% of Phase 5 and Franklin 41%.

Brentwood's McEwen Drive project page describes the extension as a direct link from the new I-65 interchange to the Taramore subdivision. It notes possible later connections to Pleasant Hill Road, Clovercroft Road, and eventually Nolensville, Smyrna and I-24. Brentwood also calls it "an alternative east/west route to help alleviate congestion on Concord Road, Crockett Road, Moores Lane, and Split Log Road." Brentwood will extend the road through Taramore itself in a later project.

For buyers, that stated purpose matters more than any other detail in either city's plans. Both cities are building a through-route meant to give cross-county drivers an option besides Concord, Crockett, Moores and Split Log. Drivers who take that option will head for the McEwen interchange on I-65, and the road there runs past McEwen's neighborhood entrances. Stuckey described the corridor in the same terms in January 2025, as "an important east-west connection across our community, but ultimately across the county."

When it's finished, the road will be wider, smoother and lit, with a multi-use path for walking and biking. It will also carry more drivers who are passing through than the road carries today.

How this compares with other Franklin corridors

East McEwen is the corridor in Franklin where change arrives soonest. On Franklin's capital improvement list, the Mack Hatcher intersection upgrades at Hillsboro Road and Del Rio Pike are scheduled to start construction in 2026 and finish in 2027. Widening Mack Hatcher's southeast section, from Highway 96 East to Columbia Avenue, isn't expected to start construction until 2032, even though WSMV reported in May 2026 that the state had raised its commitment to $40 million. The Franklin Road widening between Mack Hatcher and Mallory Station is still in early planning, with a tentative completion date of 2032.

So in most of Franklin, the commute you test-drive today is close to the one you'll have for the next five years. On East McEwen, the commute will change twice. Construction runs through about 2028, then the new connection toward Brentwood is scheduled for 2030. I cover more of the trade-offs between Franklin's newer and older areas in this piece on newer communities versus established neighborhoods.

Before you write an offer off McEwen

When I show a home along this corridor, I want buyers to know three things before we talk price. First, which way the subdivision's entrance takes them: onto McEwen, or out toward Liberty Pike or Wilson Pike. Second, how the house sits relative to the new four-lane section, since a home that backs onto the right-of-way will feel the work differently from one several streets in. Third, whether they'll still live there in 2030, when the eastern connection is scheduled to open. If they will, their time in the house will include both the finished road and the regional traffic it was designed to carry.

For sellers, the same timeline is useful in the listing. Buyers who see a construction zone on the way to a showing are looking at a few hard years. Buyers who understand the plan see a home on what Franklin and Brentwood are building into a main east-west route. If you're coordinating a sale and a purchase across this stretch, my notes on timing a Franklin move-up cover how to sequence the two.

If you own a home off East McEwen, or you're deciding whether to buy one, I'd be glad to go through the construction timeline house by house with you, down to the entrance you'd use. Suzy Sells TN can start with a free home consultation, and we'll look at the 2028 and 2030 versions of the road together.